After-Tax NPV of
After-Tax NPV of
The Study updates the Company’s 2022 feasibility study and reflects current metal price assumptions, capital and operating cost estimates, and a revised mine plan. The economic analysis is based on assumed metal prices of
Total recoverable ounces of gold have increased 7% from 361,800 ounces to 385,800 ounces. The revised production schedule extends the Project’s mine life from 7.8 years to 9.3 years. The Study outlines significantly improved project economics, including an after-tax NPV (5%) of
The Study includes sensitivity analysis to higher commodity prices amongst other inputs. Assuming metal prices of
The Project is planned as an underground operation with a relatively small surface footprint. Grassy Mountain received a positive Record of Decision from the
KEY HIGHLIGHTS OF THE UPDATED FEASIBILITY STUDY
All amounts in
Project Economics (at base case
- After-tax NPV (5%):
$374.7 million - After-tax IRR: 38.9%
- Payback period: 2.2 years
Project Economics (at upside case
- After-tax NPV (5%):
$608.6 million - After-tax IRR: 55.4%
- Payback period: 1.4 years
Production Profile
- Average annual gold production: 41,400 ounces
- Average annual silver production: 51,500 ounces
- Average gold mill head grade: 0.18 oz/ton (6.06 g/tonne)
- Average gold recovery: 93%
- Initial mine life: 9.3 years
Capital and Cost Structure
- Initial capital expenditures:
$189.8 million - Sustaining capital:
$65.1 million - All-in sustaining costs (AISC) net of silver by-product credits:
$1,442 per ounce of gold- Includes silver by-product credits based on average annual silver production of 51,500 ounces and an assumed silver price of
$48 per ounce
- Includes silver by-product credits based on average annual silver production of 51,500 ounces and an assumed silver price of
Mineral Reserves and Mineral Resources
- Proven and Probable gold mineral reserves of 405,000 ounces
- Measured and Indicated gold mineral resources (inclusive of reserves) of 1.36 million ounces
“The updated Study allowed us to refine expected development costs and integrate industry-wide inflationary pressures. The strong projected returns at both the base case and upside case highlight Grassy Mountain’s significant leverage to today’s gold price environment and the resulting improvement in project economics. The Study also reflects a larger mineral inventory compared to our 2022 study, further underpinning the Project's long-term potential.
We remain focused on completing the remaining permitting steps to position the Project for a construction decision. Grassy Mountain represents a compelling near-term development opportunity, and we look forward to sharing further updates as we advance toward that milestone.”
The following table summarizes key metrics from the 2022 and 2026 feasibility studies, including an upside case at higher metal prices.
2022 and 2026 Feasibility Study Metrics
| 2022 FS ( | 2026 FS Base Case ( | 2026 FS Upside Case† ( | |
| Project Economics | |||
| After-tax NPV (5%) | |||
| After-tax IRR | 22.5% | 38.9% | 55.4% |
| Payback period | 3.3 years | 2.2 years | 1.4 years |
| Production Profile | |||
| Annual gold production | 46.6 koz | 41.4 koz | |
| Annual silver production | 54.5 koz | 51.5 koz | |
| Total recovered gold ounces | 361.8 koz | 385.8 koz | |
| Total recovered silver ounces | 424.8 koz | 477.2 koz | |
| Initial mine life | 7.8 years | 9.3 years | |
| Capital and Cost Structure | |||
| Initial capital | |||
| Sustaining capital | |||
| Mining cost | |||
| Processing cost | |||
| G&A cost | |||
| Cash costs net of by-products* | |||
| All-in sustaining costs** | |||
NOTES:
† Production and capital cost metrics are unchanged across both 2026 price cases.
* Cash costs consist of mining costs, processing costs, mine-level G&A, refining charges and royalties, net of by-product credits
** AISC includes cash costs plus sustaining capital and closure costs, net of silver by-product credits, at the project level. Corporate G&A is not included.
MINERAL RESERVE AND MINERAL RESOURCE ESTIMATES
The 2026 Feasibility Study reflects a larger mineral inventory compared to the 2022 Feasibility Study, with gold reserves of 405,000 ounces, silver reserves of 625,000 ounces, and measured and indicated gold mineral resources (inclusive of reserves) of 1.36 million ounces.
Gold and Silver Mineral Reserve Estimates (US Imperial)
| Tons (‘000s) | Grade (oz/ton Au) | Gold (‘000 oz) | Grade (oz/ton Ag) | Silver (‘000 oz) | |
| Proven mineral reserves | 299 | 0.167 | 50 | 0.256 | 77 |
| Probable mineral reserves | 1,908 | 0.186 | 355 | 0.287 | 548 |
| Total Proven and Probable reserves | 2,207 | 0.184 | 405 | 0.283 | 625 |
Gold and Silver Mineral Reserve Estimates (Metric)
| Tonnes (‘000s) | Grade (g/tonne Au) | Gold (‘000 oz) | Grade (g/tonne Ag) | Silver (‘000 oz) | |
| Proven mineral reserves | 271 | 5.72 | 50 | 8.77 | 77 |
| Probable mineral reserves | 1,731 | 6.38 | 355 | 9.85 | 548 |
| Total Proven and Probable reserves | 2,002 | 6.29 | 405 | 9.70 | 625 |
NOTES:
- Mineral reserves have an effective date of
May 15, 2026 . - Mineral Reserves are reported inside stope designs assuming drift-and-fill mining methods, and an economic net smelter return cutoff grade of
$200.64 per ore ton ($221.17 per ore tonne) processed. The economic cut-off grade estimate uses a gold price of$2,750 /oz, mining costs of$141.18 /ton ($155.62 /tonne) processed, surface re-handle costs of$0.22 /ton ($0.24 /tonne) processed, process costs of$39.09 /ton ($43.09 /tonne) processed, general and administrative costs of$20.15 /ton ($22.21 /tonne) processed, and refining costs of$6 /oz Au recovered. - Metallurgical recovery utilizes the leach recovery schedule discussed in section 10 of the Technical Report Summary.
- Mineralization that was either not classified or was assigned to Inferred Mineral Resources was set to waste.
- A 1.5% NSR royalty is payable.
- Rounding may result in apparent discrepancies between tons (tonnes), grade and contained metal content.
Gold and Silver Mineral Resource Estimates – Exclusive of Mineral Reserves (US Imperial)
| Tons (‘000s) | Grade (oz/ton Au) | Gold (‘000 oz) | Grade (oz/ton Ag) | Silver (‘000 oz) | |
| Measured Mineral Resources | 33,700 | 0.015 | 490 | 0.061 | 2,065 |
| Indicated Mineral Resources | 21,887 | 0.021 | 462 | 0.081 | 1,777 |
| Measured + Indicated Mineral Resources | 55,587 | 0.017 | 952 | 0.069 | 3,842 |
| Inferred Mineral Resources | 3,779 | 0.019 | 73 | 0.056 | 210 |
Gold and Silver Mineral Resource Estimates – Exclusive of Mineral Reserves (Metric)
| Tonnes (‘000s) | Grade (g/ | Gold (‘000 oz) | Grade (g/ | Silver (‘000 oz) | |
| Measured Mineral Resources | 30,572 | 0.50 | 490 | 2.10 | 2,065 |
| Indicated Mineral Resources | 19,856 | 0.72 | 462 | 2.78 | 1,777 |
| Measured + Indicated Mineral Resources | 50,428 | 0.59 | 952 | 2.37 | 3,842 |
| Inferred Mineral Resources | 3,428 | 0.65 | 73 | 1.92 | 210 |
NOTES:
- RESPEC is the qualified person firm responsible for the mineral resources estimate.
- Mineral resources are comprised of all model blocks at a 0.008 oz/ton AuEq (0.27 g/tonne AuEq) cut-off that lie within an optimized pit plus blocks at a 0.070 oz/ton AuEq (2.40 g/tonne AuEq) cut-off that lie outside of the optimized pit.
- oz/ton AuEq (gold equivalent grade) = oz/ton Au + (oz/ton Ag ÷ 129).
- Mineral resources summarized in the table immediately above are reported exclusive of the mineral resources converted to mineral reserves. The Mineral Resource includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that this economic assessment will be realized.
- Mineral resources potentially amenable to open pit mining methods are reported using a gold price of
$3,100 /oz, a silver price of$34 /oz, a throughput rate of 5,000 tons/day, assumed metallurgical recoveries of 80% for Au and 60% for Ag, mining costs of$3.14 /ton ($3.46 /tonne) mined, processing costs of$16.33 /ton ($18.00 /tonne) processed, general and administrative costs of$2.79 /ton ($3.08 /tonne) processed, and refining costs of$5.00 /oz Au and$0.50 /oz Ag produced. Mineral resources potentially amenable to underground mining methods are reported using a gold price of$3,100 /oz, a silver price of$34 /oz, a throughput rate of 5,000 tons/day, assumed metallurgical recoveries of 92.8% gold equivalent, mining costs of$141.18 /ton ($155.62 /tonne) mined, processing costs of$39.09 /ton ($43.09 /tonne) processed, general and administrative costs of$20.15 /ton ($22.21 /tonne) processed, and refining costs of$5.00 /oz gold equivalent produced. - The effective date of the estimate is
February 28, 2026 . - Rounding may result in apparent discrepancies between tons, grade and contained metal content.
The updated S-K 1300 Technical Report Summary for the
Qualified Persons
The updated S-K 1300 Technical Report Summary was prepared by Ausenco Engineering Canada ULC (“Ausenco”) as the lead author, with contributions from independent Qualified Persons from
The scientific and technical information from the technical report summary and contained in this news release has been reviewed and verified by the QPs of Ausenco (processing, infrastructure, costs, financial analysis and overall report coordination), RESPEC (mining, mineral resources and mineral reserves), WSP (tailings storage facility), SLR (reclamation and environmental), and GMS (geotechnical), each of whom is independent of
About
Grassy Mountain is an advanced-stage development project in
About Ausenco
Ausenco is a global engineering, consulting and project delivery firm built for the minerals and metals industry. With three decades of global experience, Ausenco works alongside clients to navigate complex challenges from first study to final closure—across every phase, on five continents. Deeply rooted in the minerals and metals industry, their people combine technical depth, hands-on expertise, and hard-earned insight to deliver practical, forward-thinking solutions that reduce risk and unlock value. (www.ausenco.com).
For further information, please contact:
CEO and Director
rachel@paramountnevada.com
844.488.2233
Investor Relations
IR@paramountnevada.com
844.488.2233
Safe Harbor for Forward-Looking Statements
This release and related documents may include "forward-looking statements" and “forward-looking information” (collectively, “forward-looking statements”) pursuant to applicable
Please see “Risks Factors” in the Form 10-K filed by
Source: