Terra Innovatum Global N.V. Q3 F2026 Earnings Call Transcript
AI Conference Call Analysis
Sign in or subscribe to read.Operator
Webinar Operator
Today's webinar is being recorded and will be made available on Terra's website following the event. The question and answer session will follow this morning's prepared remarks. If you'd like to ask a question at any point, please submit it through the Q&A box at the bottom of your Zoom screen, and we will address as many as time permits during the Q&A portion. It's my pleasure now to hand the call over to Giordano Morichi, founding partner and managing director of global business development and investor relations. Giordano, please begin.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
Thank you, operator, and good morning, everyone, and welcome. Joining me today are Alessandro Petruzzi, our co-founder and chief executive officer, and Katherine Williams, our chief financial officer. On Monday, November 16, Terra Innovatum filed its quarterly report and formed thank you for the quarter ended September 30, 2026, and issued its quarter financial results and business update. This morning, we also posted our Q3 2026 business update presentation, which will refer during today's call and webcast. All these materials are available in the investor relations section of Telenovatum's website. Before we begin, I'd like to remind everyone that today's discussion will include forward-looking statements concerning our business, financial outlook, licensing activities, equipment procurement, manufacturing preparations, potential customer deployments, and commercialization plans. These statements reflect current expectations and assumptions and involve risks and uncertainties that could cause actual results to differ materially. Please refer to our earnings release, most recent form thank you, and other SEC filings for discussion of these risks. We undertake no obligation to update forward-looking statement except as required by law. Today, we will discuss progress during the third quarter and subsequent developments through the date of our earnings release. Our discussion will focus on three connected priorities, executing the work required for the first solar reactor, advancing qualified customer opportunities toward commercial deployment, and managing capital against defined milestones. With that, please turn to slide one of the presentation. Alessandro, over to you.
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
Thank you, Giordano, and thank you everyone for joining us today. The fundamental message we want to share with you today is that Terra Innovatum is moving from preparation towards execution. We are in fact procuring equipment for our first reactor, preparing manufacturing and assembly process and advancing customer opportunities towards commercial deployment. Our objective is to build a scalable, profitable business around Solo. Our first reactor is a foundational technical and regulatory step, while the supplier relationship, manufacturing processes, and customer relationship we establish today are intended to support subsequent commercial installation tomorrow. During the quarter, we entered into a procurement agreement with Oden for steam turbine and generator equipment. We also advanced NRC pre-application readiness activities and entered into a non-binding initial letter of intent with Waking Group for potential data center deployment in Latin America. Subsequent to the quarter end, we progressed the manufacturing preparation with ATB Riva Calzoni, reported procurement and down payments for major reactor components, and completed sharing all 18 draft preliminary safety analysis report chapters with the NRC for its readiness review. We remain completely focused on technical execution and continue to target our first of a kind reactor deployment in 2027, with commercial deployments beginning in 2028, subject to the regulatory approval and execution milestones. Our priority today is to ensure these workers stream advance in parallel. So we need to align regulatory and technical milestones, supply chain execution, and customer commitment to support a coordinated and scalable solo deployment strategy. Moving now to slide two. Our industrial strategy is built around established supply and manufacturing partners. We are working with companies that bring relevant equipment, fabrication, and industrial capability to the solo program. This approach allows us to concentrate our resources on engineering activities, licensing, integration, and deployment while drawing on existing manufacturing infrastructures. During the third quarter, our agreement with Oden advanced the procurement of steam turbine and generator equipment for the first solar and potential subsequent units. Following quarter end, We reported that procurement had commenced and down payment had been made for graphite components from Mersen, turbine and steam generator equipment from Oden, and air cooler condenser from SPG Drying Pooling. These steps mark a shift from supplier planning into funded equipment procurement. We are committing capital to critical components and supporting the manufacturing and delivery activities required to build our first solo reactor. These are not simply expressions of the intent, but actual financial commitments supporting equipment production, supply delivery schedule and our target FOC deployment. In October, we progressed the assembly planning, manufacturing procedure and the devaluation of dedicated factory space at ATB Rivacalzone. That work supports both the first reactor and the development of repeatable manufacturing processes for future units. We also progressed equipment testing with Goldrocky. A helium circulator of the same design intended for Solo completed a four-hour hot-running test successfully. Two additional helium blowers were being acquired and prepared for non-nuclear system testing and interface evaluation. And this testing helped us evaluate equipment performance and interface height of integration into our first reactor. Alongside this commitment, we are also in advance in discussion on the remaining major equipment package. Each component has its own specification, production requirement, and delivery schedule today. Our next priority is to coordinate procurement and delivery with the testing and assembling activities required for the first reactor deployment. Please now turn to slide three. And obviously, licensing remains a central part of the development program. During the third quarter, following our July request, the NRC began its initial pre-application readiness assessment. The initial scope included the environmental report and nine draft preliminary safety analysis report chapters. This process provides an opportunity to receive feedback and identify information needs as we prepare for our formal construction permit application. Subsequent to the quarter end, as planned, we completed sharing all 18 draft PSAR chapters with the NRC for Readiness Review, announcing these important milestones in early November. The PSAR is a core element of our planned reconstruction permit application, and completing these chapters represents substantial engineering and safety analysis work for us. This is not an LRC approval or acceptance of a formal application, but this is a milestone we have achieved as publicly announced one year ago. Our focus now is to address feedback, continue readiness review engagement, and advance the application material required for the next stage. And our engineering and execution team are coordinating this application preparation with equipment specification, manufacturing plans, and site requirements. Moving on to slide four, we are approaching the first solar reactor with subsequent customer deployments in mind. That means working with suppliers on repeatable manufacturing process, coordinating equipment specification and assembly requirements, and evaluating customer opportunities against our delivery capabilities as we prepare for commercial deployment. Our first reactor established the technical regulatory foundation, but our commercial work is focused on converting customer demand into a definitive agreement and executable deployment plan. The two work streams inform each other. Customer requirements help shape deployment planning, while the progress on licensing, procurement and manufacturing help us define credible delivery plans. Across the business, we are advancing three near-term priorities in parallel. First, advancing NRC readiness review work and construction permit application preparation. Second, progress measure equipment procurement, delivery planning, testing, and assembly preparation. And third, advancing qualified customer opportunities towards definitive agreement with the deployment requirements aligned to our execution capabilities. These are the steps we will use to measure and communicate our progress towards deployment. I will now turn the call over to Cathy to discuss our financial results and the capital allocation.
Katherine Williams
Chief Financial Officer
Thank you, Alessandro, and good morning, everyone. I'll ask you to now please refer to slide five of the presentation. Terra Innovatum reported $61 million in net income for the third quarter of 2026. and we ended September 30th, 2026 with $82.4 million in cash and cash equivalents compared with the $91.1 million at June 30th, 2026. Our financial focus is on managing that capital against the activities that are required to bring the first solo reactor into operations. Those activities include licensing, engineering, equipment procurement, supplier commitments, and manufacturing readiness, alongside the people and public company infrastructure that's needed to execute our program. As procurement progresses, the timing of supplier payments and equipment deliveries will influence quarterly cash usage. we are managing those expenditures against the contractual requirements and execution milestones with continued focus on overhead and organizational cost. Advances to suppliers total 2.6 million as of September 30th, representing advanced payments to third-party engineering and component suppliers under the solo development agreements. Our total operating expenses were $7.1 million during the third quarter, including $1.7 million of development cost and $5.4 million of general and administrative expenses. As noted, net income was $61 million or $0.55 per basic and diluted share. This included $67.5 million of non-cash gains from changes in the fair value settled contingent and warrant liabilities. Our industrial model relies on working with established manufacturing partners. That allows us to direct capital towards our reactor program equipment integration activities while leveraging the existing industrial capabilities. Looking ahead, our priorities are disciplined capital allocation, clear reporting, and maintaining the financial resources needed to support the next stage of execution. With that, I'll turn the call back to Giordano for our commercial update.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
Thank you, Kathy. And I'd like everyone now to please turn to slide six. Our commercial strategies focus on moving beyond expression of interest and translating qualified customer demand into binding reactor purchase agreements and executable solo deployment plans. This requires aligning customer power requirements with site readiness, regulatory pathways, technical specifications, and delivery schedules while establishing clear commercial commitments and financial milestones. During the third quarter, we advance our international commercial pipeline through the non-binding LOI agreement with Wacom for the potential deployment of up to eight megawatts electric for the behind-the-meter solar capacity supporting Direct TV, Latin America, and Sky Brazil data center infrastructure in Argentina and Brazil. Moving to slide seven, please. More broadly, the commercial priorities are evolving beyond, again, traditional letters of intent, the LOIs, and the Memorandum of Understanding, the MOUs, towards structured commercial frameworks that establish the foundational for definitive reactor purchase agreements. These frameworks are designed to define reactor quantities, deployment schedules, contractual responsibilities, payment structures, potentially including upfront reactor reservation deposits, and milestone-based payments. As we progress toward the Definitive Agreements, we believe this approach can strengthen customer commitment, improve revenue visibility, and support future deployment. Our U.S. commercial platform remains central to this strategy, supporting customer engagement, strategic partnerships, and deployment planning, while we continue advancing qualified international opportunities across data center, industrial infrastructures, defense, healthcare, especially for the radioisotope production, and other energy-intensive applications. Ultimately, our objective is not simply to expand the pipeline, but to convert qualified commercial demand into tangible binding orders, secure customer commitments, and predictable deployment schedule. We will continue to provide updates as material commercial milestones are achieved. With that, we move to the questions. I already see some of the questions from H.B. Wainwright, Stonex, and P. Riley. I will take it as they came in. Thank you, Samir, for joining us. I'll run it through the first one and continue with the rest. Does the fact that you are making up from payments, as listed in slide 2, indicate the completeness of the engineering design? Do you expect any change to the design that could affect these agreements? Alessandro?
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
Actually, all our technical activities are following the schedule and the roadmap we established one year and a half ago. So far, the design of the graphite and stainless steel vessel are really in the end phase, very close to the manufacturing drawings, what is called manufacturing drawings. We do not expect any major change in the next few weeks. Our intention is to complete those steps by the end of the year and to start the real work for the manufacturing of those components at the beginning of next year. Minor changes may be still expected on the layout of the plant. We are still working and cooperating in particular with the company that will support us for the site application in Rock City at Mirror Park. But no one of them, in our view, is affecting the cost that we foreseen one year and a half ago. And this, I think, we think, is one of the big achievements we have achieved. We have realized in this one year and a half, not only we submitted the construction permit in just less than 14 months as announced, but thanks to the fact that our reactor is made of the shared component and the supply chain exists today, our estimation of cost made one year and a half ago are very in line with the real cost we are now supporting today for procuring those material components.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
Second question from Samir H.V. Wainwright. It still regards the NRC licensing. Nature of commitments, lessons learned. Can we leverage the commitments done so far? And there has been any items that take longer than expected. How quickly do we respond to the NRC?
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
We have a continuous relation with USNRC, at least two or three meetings per week. Unlikely, I can attend only one while my team is attending all, and I would like to attend more, but... The situation is very fluid. We are now entering a very epic period because we advanced for the submission of those 18 chapters. We should receive the readiness review in the upcoming few weeks in order to stay in line with our construction permit next year. The project itself, the simplicity of the project, the low power, the very limited number of components made the process definitely easy from the technical point of view, from the safety point of view. but this is just a part of the licensing process. There is an additional part of the licensing process which involves also the construction, the siting and the oversight of the work. There are topics that we are now really discussing with USNRC but again so far there is no evidence of any event that may cause delay in our application. And in particular, this is because, again, our reactor is strongly based on fundamental safety principle of physics, which made the application at the end more straightforward than other reactors.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
And then last from Samir H. Wienwright, imagine it's December 2028, what would you expect to see at the first-of-a-kind site? Sorry, Giordano, can you repeat this? Imagine it's December 2028, what do you expect to see at the first-of-a-kind site in Rock City? December 2028.
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
We would hope that will be even before December 2028. We are working really actively to do by end of 2027. This is our goal to bring the reactor in the United States from the factory in Italy and to start the deployment of the reactor in 2027, beginning of 2028 with the operating licensing application. I think this will be a big event for everybody. It will be the first micro-reactor that is immediately connected to an industrial application because this is also important to outline. The Rock City and Mirror Park is an industrial site. They need power and our reactor, our first of a kind, will provide a reactor to this. So I would imagine a very great day for us, and very important because anyway we fully understand that the execution is fundamental for the success of this project. We are working very hard as Giordano said for the commercial application. We will continue but from the other side we understand that the realization of the first of a kind in Rock City will be a sort of cliff edge effect for our marketing.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
Thank you, Ale. Subhash Chandra, Sonex, thank you for joining. As a second phase of the readiness review started, Alessandro?
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
The second phase of readiness review will start immediately after it is completed and we expect that it will occur before the end of this year. So we are again continuously having meetings with the USNRC. There is continuous feedback and answers to this feedback. All our team is involved in this. This is the priority of our team today or the technical team to complete the readiness review. So, immediately after this, we will start and we will continue, I have to say, the work on the operating license, which has been already started. So, the next step, obviously, is to continue in the next six months of the year, from January to June, July next year, to support USNRC for getting the construction permit application.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
and one for Kathy, still from Subash. Of the $17 million first of a kind budget, how has the budget been spent so far?
Katherine Williams
Chief Financial Officer
So out of the $70 million for the first of a kind, that is where our expenditures have been reflected in the 10Q because that is all that we're working on right now, is the first of a kind. So what you will see is that we began to 2026 with a little over $100 million in the bank. At this point, we have the 82 million of cash still in the bank. All of the expenditures, again, have gone for the first of a kind. For the $70 million, which is 2026 and 2027, we have spent about one third of it. We're still on track with all of our planned expenditures. And right now, it looks like with the agreements we have with suppliers, we will come in right on budget for the $70 million. And we will still have between $20 and $30 million remaining to help us with the commercialization efforts.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
and part of the regulatory cost of this question related to this, Kathy? I'm sorry, Gio, can you? How much would it be the regulatory cost within those $70 million?
Katherine Williams
Chief Financial Officer
The regulatory cost of that. So we have budgeted around $15 million.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
Thank you. We have a few still from Subhash on 80% list of material suppliers. What is the left 20%? There's a question related to the fuel and the EPC, if it's been secured. And is NKLR the EPC? Alessandro?
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
Fuel is definitely the most important element in the reactor. We are actively finalizing the procurement of the fuel. And for that, the specification for the fuel have been already submitted to our fuel vendor.
Operator
Webinar Operator
So we are interacting.
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
As you know, our fuel is low-enriched uranium fuel. The amount of fuel that we need is not a concern for any fuel vendor. The amount that we need is something that the current industry can produce easily in less than one day. So there is no problem of getting the fuel. We are always interacting with the fuel vendor because The focus is the fork, but the focus is also the commercialization as well. So it's a larger discussion that we are having, and this should be completed in a few weeks, I would say, starting from the beginning of the year 2028. I don't know the second part. Can you remind me the second part of the question, Giordano?
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
Regarding the EPC. EPC.
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
EPC, we have started to work in Rock City Admiral Park. We have done Boreole. We started the analysis, the geographical analysis with the analysis of the soil. We are interacting with our EPC for organizing the work on site. And this work is something that is going to grow up in the next, again, few weeks. We will move from the technical activities related with the construction permit to the activities that are more engineering-based related with the siting.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
And related to what you just said, Alessandro, does the rock city require separate site permitting or is it part of the construction permit?
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
No, it's part of the construction permit. We already submitted the environmental safety analysis. We are proceeding. We need to add elements to this coming from the analysis of the soil, which has been done recently, just a few days ago, with positive results. So you will see upcoming news in respect to this very, very soon for the site.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
We have one from Ryan Finks. Thank you so much for joining from B. Riley. As we're working with the NRC and come closer to submitting the construction permit application, has the NRC given you an indication of a potential review timeline
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
Officially, no. Formally, we are having this discussion with USNRC since the first engagement. We know that our reactor is a very simple design. We know that the reactors, which were much more complex than our terminated construction permit in less than 18 months, even in 12 months, so even though formally there is definitely no engagement from USNRC to commit any date, there is a lot of elements, the simplicity of the design, our full support to this activity, our experience in doing licensing that helped to understand that we are still on track to get the construction permit in 2027, in the second half of 2027, as it is our goal.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
There's a second side to the question, maybe I can answer that. When do you think customers will be able and move comfortably toward the binding order and when they will likely wait on, or would they likely wait on completion for the first of a kind? I think having secured again 80% of the supply chain, progressing constantly with the USNRC has big advantages for us in terms of the commercialization. All of our customers have been vetted in terms of KYCs and so forth. So the main point is really moving again from the LOIs and the MOUs, which are Alessandro Petruzzi, Giordano Morichi, Marco Cherubini on how comfortable the customers are moving forward. What we can say is that we have been working thoroughly for the past year. We have a very good engagement with all of our customers and definitely having advanced our licensing and the supply chain securement puts them in a good position to proceed with the next steps of the framework, which will then lead to the binding agreement. We've planned to have a portfolio in 2020, mid-2027 to end of 2027 for the future supply chain demand and growth for the commercialization. But we're working very hard to execute, if possible, before that. One more question from Georgia Cantus from Canaccord Genuity. Thank you for joining. Can you please discuss your updated business model and cost structure per the 10Q? Cathy?
Katherine Williams
Chief Financial Officer
Definitely we can. So per the 10Q, our cost structure is progressing to keep our overheads at the lowest level possible. Since we are planning that everything will be manufactured by someone else, we are not doing any vertical integration of all the supply chain. And we're using existing suppliers, existing manufacturing capabilities. So with that, we keep our overheads lower. The focus getting to the first of a kind is with getting the right engineering and the right supplier contracts in place. That is why we're confident we'll stay within the 70 million that has been reported for the first of a kind. As we move forward after the first of a kind into commercialization, We still will have money to begin the commercialization, but that's where we'll need to have the firm contracts in place in order to have the advance payments to suppliers and where we have talked about the potential maybe for another capital raise. But that will not happen as a result of first of a kind. We have the cash in hand to complete the first of a kind in Rock City and prove that the design works.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
and then can you please discuss projected cash burn for 2027?
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
If I may add, sorry Giordano, so far the positive aspect of this project we think is staying in the estimation of the cost because the supply chain exists today. So this gave us an uncertainty on this estimation, which was very narrow, and we confirmed a lot of them during this one year. What I'm going to say is that The 70 million obviously include not only the reactor construction, but all the work of our licensing, as Cathy said, and also the work that the people for the safety analysis group and licensing group has to perform, including the site. The estimation we have for the first of commercial reactor are today still aligned with our forecast done time ago, two years ago. And because we base those estimation on those costs provided by the supplier. This is to say that in our business model, As we think that we will not integrate the supply chain, at least during the first phase of the commercialization up to 2030, 2031, up to we don't reach a very high number of units per year. And second, as the costs are today almost known to us, and third, as we intend to go in the deployment phase with advanced payment, as Cathy said, this means that basically our business model will be such that we will not be lost in the first phase of commercialization. This is our goal.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
Thank you, Ale. Bear with me. Can we please discuss the mechanics of coordination with part 57 year end, year 2026? And do you expect to get this push into 2027?
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
This will be a nice gift for us and for all the nuclear micro reactor ecosystem, you know. Part 57 now has been, as far as I understand, moved to be executive in February 2027. The process in Part 57 starts to become clear, more clear to everybody. And the time to get the license under Part 57, as you know, is 12 months. So this is a very important point of internal discussion inside the team, because whenever the PAR57 will become executive, several options will be available to us. Definitely continuing the licensing under PAR50, but also the evaluation of to start in parallel a PAR57 commercial license. This is what we are also organizing internally, creating a team that already have as goal the activity related with part 57 more than the part 50.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
And one more from George, kind of for Cathy, a little bit more in depth on the cash print for 2027.
Katherine Williams
Chief Financial Officer
Certainly. The expected cash burn for 2027 is between 30 and 35 million. It's primarily directed now for 2027 with the suppliers to have the deliveries of the equipment that's needed.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
We have a couple of more questions and I believe this will conclude the Q&A. We have one from Graham Takanaka. Which specific milestones are needed to achieve actual binding orders and what size of advance payments could come from customers on receiving those binding orders? What today we're discussing is 25% to 30% down payments on the estimated cost of the reactor, which we have announced throughout the year. These are the numbers we're working through. Of course, these are the stages where we're negotiating those framework agreements. There are very detailed documents as discussed. We'll be able to provide more information when there's an advancement on those. On Richard Longgreen, Goldman Sachs, quick progress in relation, thank you very much. What is currently the biggest bottleneck preventing Terra Innovatum from transitioning from the promising technology platform to commercially deployable and revenue-generating business? So bottleneck on execution, and what is the realistic timeline to resolve it? I will leave this to Alessandro to start.
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
Yeah, I may start, and then everybody, Katie and Joe, can... can comment. I think this is, you know, part of the innovation. Yesterday night I was discussing with some of people that You need to go back maybe to the time when there was the big cell phone, the huge one, and who can get this? Rich people or only people that really can need this cell phone? But for a nuclear product, Maybe the situation is a little even more complicated than this because it's nuclear, so there is still something, some elements more. It's problematic because you cannot sell the reactor to everybody because to sell the reactor, you need to have end user statements for what you are doing to use. You cannot sell just to the first person in the street. So there is some elements that make this market a little more complex than any other market. This is to say what? That advancing the work and watching the steps that we are executing in terms of safety analysis report, in terms of supply chain, is something that can create confidence in the market to arrive at the end, to the final stage of transforming the non-binding in binding. But it's an evolution process. We are confident of our work and we will continue to work as much as we can to transform those non-binding in binding. But from the other side, I think is the Execution itself is the realization of the FOC on site. It's the time when the FOC will reach the site in Illinois. So even when the vessel will be ready at ATB, that will be a sort of cliff edge in the behavior of the customer. And in terms of timelines, we are still on our timelines. We want to become commercial by 2028.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
Kathy, any remarks on this? Any bottlenecks that you see on your front? And how do we get to this revenue generating?
Katherine Williams
Chief Financial Officer
That will certainly be an exciting day for all of us when we get there. The only bottleneck would be having the customers believe in the product. getting their agreement that yes this is what they want and where we will go forward and of course we're continuing to do that every month as we advance with the process with the NRC and that we will get the licensing in place everything that's required and it will perform the way that we have said that it will perform which is why the first of a kind at Rock City is so important A lot of the discussions we are having with potential customers is focusing now on, OK, how do we structure a contract that will allow us to go ahead and say we want this product? But we also want some assurance that if this gets delayed or this gets delayed, recognizing we're dealing with a government regulation that This will be what the secured price still is. And it's getting more favorable with every discussion we have because we have stuck to our plan. We have delivered exactly what we said we were going to deliver and met all the milestones. As Alessandro says, we have good security in what the cost of the reactor is going to be at this point. We have placed the majority of contracts needed with suppliers. So we know what the price is. Again, it has been secured. So it's working with the customers to get their confidence that now is the time to place the order. And that's part of our big focus, as you know, Gio, that we're trying to secure those orders for proof that we are commercially ready.
Giordano Morichi
Founding Partner and Managing Director of Global Business Development and Investor Relations
And I think if I can ditto what Cathy said, you know, one item that I really would like the company, sorry, the investors and the analysts to focus on, and I think you appreciate it being part of this call, is the fact that Tata went to the market with the R&D done, with a very strong engineering background. We're a crawl-walk approach company. We're very reliable in terms of deliveries on the USNRC, as we've demonstrated. What we said we would do, we have done. We're excelling at. And thanks to that, thanks to the technology that is the underlying element of the whole structure of the whole machine, we're able to get to this framework agreements, as Cathy explained, and we're able to discuss some of the preliminary details, which would then lead to the binding aspect. So I think we're in a strong position to continue this process with the customers that have been vetted again. and hopefully we'll give some good news soon. But we're working very diligently on these items. And I think this is the end of the Q&A with all the questions. I would really like to thank everyone joining the call today, investors, analysts and all of the Tata family. Again, thank you, operator. And I will turn now to Alessandro for the closing remarks.
Alessandro Petruzzi
Co-Founder and Chief Executive Officer
Thank you, Joe. So please turn to slide eight. As a summary, during the quarter and subsequent weeks, we advanced the licensing preparation, equipment procurement, manufacturing readiness, and a defined potential customer opportunity with Viking Group. From here, the milestones to track are basically three. First, the NRC readiness review feedback with the advancement of our construction permit application, as well as the initial preparation for our operating licensing application. Second, the procurement of remaining major equipment and site readiness work. And third, the conversion of qualified customer opportunities into binding reactor purchase agreement with a reservation deposit and milestone-based payment. Together, these milestones will demonstrate progress on two connected objectives, bringing our first solar reactor towards deployment and, second, establishing the industrial and commercial foundation for a scalable business. So, we will continue to manage capital against these priorities and communicate material progress as it occurs. Thank you, so far, for your continuing interest in Terra Innovatum, for joining us today, and with that, operator, we conclude the course.
Operator
Webinar Operator
Thank you, everybody. Thank you, Tarot Team, for joining us today. Thank you, audience, for joining us as well. This concludes today's webinar and you may disconnect at your convenience. Thank you. Have a great day. Thank you, everyone.